Methods and systems for deploying equipment required to meet defined production targets
Abstract
Methods and systems determine at least one production constraint for a material loading system and a material processing system; estimate an effect of entropy on a cycle time of a material conveying system to produce a future cycle time estimate; estimate an effect of entropy on a material processing time to produce a future material processing time estimate; predict whether a delay will occur during the operation of the material loading, material conveying, and material processing systems; estimate a duration of the predicted delay; determine a loading system capacity and a conveying system capacity required to meet the defined production target based on the production constraint and estimates of the future cycle time, the future material processing time, and the duration of the predicted delay; and deploy one or more material loading and conveying systems to meet the determined loading and conveying system capacities.
Interactive Citation Constellation Global Citation Ranking
Interactive SVG Citation Constellation renders in Rust/WebAssembly. Prior art cited: 24 · Forward citations: 3.
Claims (1 — 1 Independent, 0 Dependent)
- Claim 1Independent Claim
A system for deploying equipment required to meet a defined production target for a material processing system, the equipment including at least one material loading system and at least one material conveying system, comprising: a production constraint module, said production constraint module generating at least one of a process delay time and a planned downtime for at least one of the material loading system and the material processing system; a stochastic simulator; a cycle time and variance module operatively associated with said stochastic simulator, said cycle time and variance module pr
Technical Overview & Description
Full multi-page specification text is archived at the issuing office. Read complete official specification ↗
Cited By — Indexed Forward Citations (3 of 3 total)
References Cited — Backward Prior Art (24)
Non-Patent Literature (3)
- Asbjornsson et al. (2016), “Modelling of discrete downtime in continuous crushing operation,” Minerals Engineering, 98, 22-29. Doi: 10.1016/j.mineng.2016.07.003. Abstract; p. 23 para 7; p. 26 para 4; p. 27 apra 1,2.
- Jaoua et al., (2012), “Specification of an intellegent simulation-based real time control architecture: Application to truck control system,” Computers in Industry, 63, 882?894. DOL: 10.1016/j.complnd.2012.07.002; Abstract; p. 884 para 3; p. 888 para3; p. 889 para 13; p. 891 para 2.
- PCT Internatinal Serch Report and Written Opinion, dated May 28, 2021, for corresponding International Application No. PCT/US2021/022494, 10 pages.