{"pub_number":"US12378743B2","doc_number":"12378743","country":"US","kind_code":"B2","patent_type":"utility","status":"active","title":"Multi-piece pre-assembled raft foundation and construction method thereof","abstract_text":"A multi-piece pre-assembled raft foundation is provided and includes pre-assemble bottom layer rebars of foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars. The pre-assembled raft foundation is transported to a construction site for final assembly. A construction method of the multi-piece pre-assembled raft foundation is also provided.","claims":[{"number":1,"text":"A pre-assembled raft foundation, comprising: a plurality of bottom layer rebars of a foundation slab including a plurality of bottom layer sections and a plurality of first vertical sections connected to the bottom layer sections wherein the bottom layer sections and the first vertical sections are composed of a plurality of U-shaped rebars and a plurality of steel bars disposed on the U-shaped rebars; a plurality of foundation steel columns disposed on the bottom layer sections and including a plurality of columns and a plurality of vertical sections disposed at tops of the columns; a plurality of upper layer rebars of the foundation slab disposed on the bottom layer rebars of the foundation slab and including a plurality of top layer sections and a plurality of second vertical sections connected to the top layer sections wherein the top layer sections and the second vertical sections are composed of a plurality of U-shaped rebars and a plurality of steel bars disposed on the U-shaped","independent":true},{"number":2,"text":"The pre-assembled raft foundation of claim 1, wherein an outer part of a frame of the pre-assembled raft foundation is built with a formwork and the formwork is a removable formwork or a non-removable formwork.","independent":false,"depends_on":[1]},{"number":3,"text":"The pre-assembled raft foundation of claim 1, wherein the vertical sections and the horizontal sections are disposed with a plurality of first elements thereon for connecting to the beams and columns; each of the first elements have a through hole and an internal thread through an internal surface of the through hole; both ends of each of the first elements are connected to the horizontal sections and the beams and columns respectively; and both ends of the internal thread of each of the first elements have an internal guide section respectively.","independent":false,"depends_on":[1]},{"number":4,"text":"The pre-assembled raft foundation of claim 1, wherein the vertical sections and the horizontal sections are disposed with a plurality of second elements thereon for connecting to the beams and columns; each of the second elements are a frame body having a plurality of positioning holes with the horizontal sections and the beams and columns insert thereinto, and a containing space through the positioning holes; and each of the second elements hold up a mounting element to be disposed on the horizontal sections and the beams and columns so that the horizontal sections and the beams and columns are mounted on the frame body.","independent":false,"depends_on":[1]},{"number":5,"text":"The pre-assembled raft foundation of claim 1, wherein the vertical sections and the horizontal sections are disposed with third a plurality of elements thereon for connecting to the beams and columns; each of the third elements are a backing plate made of carbon-based materials; the backing plate is configured to withstand a high temperature of over 1500 ° C.; and an outer appearance of the backing plate has an arc shape or a flat shape, or is a flat plate with a groove.","independent":false,"depends_on":[1]}],"description":"FIELD OF THE INVENTION\nThe invention relates to raft foundations and more particularly to a multi-piece pre-assembled raft foundation and construction method thereof.\nBACKGROUND OF THE INVENTION\nIn general, during the construction, all needed rebars will be delivered to and stored in the construction site for construction workers to tie the rebars and build a formwork before grouting. According to the current construction practice, from the start of tying rebars to the last task of demolding rely on labor-based construction.\nTherefore, to construct a building is considered a labor-intensive operation. When a construction project highly depends on workers to carry out the task will likely result in a slow progress in construction and the vast volume of unused rebars piled up in the construction site may heighten the risk of property theft. Furthermore, when there is a need of secondary grouting for a structure, if it is not carefully done, cold joints may occur after the grouting that damage the concrete structure.\nThus, the need for improvement still exists.\nSUMMARY OF THE INVENTION\nIt is therefore the first object of the invention to provide a pre-assembled raft foundation that reduce construction labor and time.\nThe secondary object of the invention is to provide a pivot element for adjusting the installation location so that the rebar installation is more convenient and simple, and the cost of material consumption is less.\nTo achieve the aforementioned objects, the pre-assembled raft foundation of the invention comprises the bottom layer rebars of the foundation slab, foundation steel columns, upper layer rebars of the foundation slab, and foundation rebars.\nThe bottom layer rebar of the foundation slab comprises bottom layer sections and the first vertical sections that are connected with the bottom layer sections; the bottom layer section and the first vertical section are composed of a plurality of U-shaped rebars and steel bars that are installed on the U-sha","inventors":[{"name":"Fu-Yuan Lu","slug":"fu-yuan-lu","city":"Kaohsiung","country":"TW"},{"name":"Ju-Chuan Ko","slug":"ju-chuan-ko","city":"Kaohsiung","country":"TW"},{"name":"Ying-Ying Lu","slug":"ying-ying-lu","city":"Kaohsiung","country":"TW"},{"name":"Chien-Hui Lu","slug":"chien-hui-lu","city":"Kaohsiung","country":"TW"},{"name":"Cheng-Yu Lee","slug":"cheng-yu-lee","city":"Kaohsiung","country":"TW"},{"name":"Mei-Hua Chien","slug":"mei-hua-chien","city":"Kaohsiung","country":"TW"},{"name":"Guang-Le Su","slug":"guang-le-su","city":"Kaohsiung","country":"TW"},{"name":"Sen Taner","slug":"sen-taner","city":"Kaohsiung","country":"TW"}],"assignees":[{"name":"Jyu Sin Steel Co., Ltd","slug":"jyu-sin-steel-co-ltd","country":"TW"},{"name":"Cheng Chi Steel Co., Ltd","slug":"cheng-chi-steel-co-ltd","country":"TW"}],"examiners":[],"cpc_codes":["E02D 2300/0034","E02D 27/08","E04C 5/0631"],"ipc_codes":["E02D 27/08","E04C 5/06"],"filing_date":"2023-02-17","pub_date":"2025-08-05","grant_date":"2025-08-05","expiration_date":"2043-02-17","family_members":[],"citations_made":[{"pub_number":"US8544227B2","category":"examiner"},{"pub_number":"US20120047835A1","category":"examiner"},{"pub_number":"US20160108618A1","category":"examiner"},{"pub_number":"US20160108619A1","category":"examiner"},{"pub_number":"US20170022699A1","category":"examiner"},{"pub_number":"CN205576955U","category":"examiner"},{"pub_number":"CN111005504A","category":"examiner"},{"pub_number":"CN111042177A","category":"examiner"},{"pub_number":"KR20210016812A","category":"examiner"}],"non_patent_literature":[],"drawings_count":0,"source_id":"uspto_patent_grants","upstream_forward_citations":0,"metrics":{"forward_citations":0,"indexed_forward_citations":0,"backward_citations":9,"npl_citations":0,"citations_per_year":0.0,"pagerank":0.0,"citation_rank":3479188,"pagerank_rank":3479188,"velocity_rank":3479188,"family_citations":0}}